Hither Green Lane
Six apartments above a ground-floor commercial unit.
The brief
Six apartments above a ground-floor commercial unit.
Scope and delivery
Three-storey construction including demolition, underpinning, ground beams, reinforced-concrete slab, steel framing, composite decking, pitched and flat roofs and M&E connections. Cycle and refuse provision formed part of the scope.
Technical considerations
High groundwater required specific arrangements during underpinning and groundworks.
Project record
Location: Lewisham, London. Project duration: 15 months. Project descriptions are drawn from Technocrates Construction's published company brochure and website. Budgets, verified completion dates and client-approved outcome measures have not yet been supplied.